Work In Progress (W.I.P) Schedule

Instruction for completion:

  1. Enter name of project
  2. Enter amount of contract, including all change orders
  3. Enter your anticipated total cost of project
  4. Enter your amount of actual coast incurred to date
  5. Enter amount of actual billings submitted to date (including retainage)
  6. Enter date project began (Month/Year)
  7. Enter anticipated date of project completion (Month/Year)
Contractor:
As of:   
Please complete the following:
(1) Job Name:   
(2) Current Contract Amount:   
(3) Current Estimate Total Cost:   
(4) Cost to Date:   
(5) Billed to Date:   
(6) Start Date:   
(7) Completion Date:   
Add another job:   


 


 